Florence Replenishment Project (2019)


KEY DOCUMENTS

Project Construction Map

Area of Detail - 3/20/2019  (Reach 2 & 3 – Indian Beach/Salter Path)

Area of Detail - 3/20/2019  (Reach 1 - East EI)

Fact SheetFlorence (2019)

Typical Cross Section (Plan)      Typical Cross Section (constructed)


PROJECT UPDATES
(please scroll further down for an interpretation guide and general project overview) 

3/20/19 - Beach nourishment continues to progress eastward towards SummerWinds from the active submerged pipe landing (see March 20, 2019 PROGRESS MAP).   The dredge Liberty Island is now going to be accompanied by the second dredge (Ellis Island) a little earlier than first scheduled and should arrive the 1st week of April.   Both dredges will work in tandem to complete Reach 1 (East Emerald Isle – SEE MAP).

3/18/19 REACH 3 COMPLETE - Reach 3 (“east” Indian Beach and Salter Path) was completed yesterday (3/17/19), and subsequently the first load of sand was delivered to Reach 2 - SEE 3/18/19 PROGRESS MAP.  Beach nourishment activities are now progressing eastward from the 2nd submerged pipeline landing, and will be “flipped” westward once the eastward run is completed.  Also, the submerged line for Reach 1 in Emerald Isle has been installed near 16th Street (see MAP).   

Photos (March 18, 2019)
Photo 1
Photo in Reach 2 Photo 2


3/15/19
- Strong productivity continues and Reach 3 (Indian Beach/Salter Path) could be completed this weekend (see 3/15/19 Progress Map).  If so, dredging/pump-out operations will move to Reach 2 in Indian Beach where nourishment will progress eastward off the 2nd pipeline landing.

3/13/19 – Productivity/progress remains strong.  Great Lakes Dredge & Dock (GLDD) has completed ~3,000 linear feet of the project in less than 5 days and the eastward leg from the first subline landing in Reach 3 (Indian Beach/Salter Path)  is complete - see photos below.  GLDD begun progressing west from the subline landing this morning (SEE 3/13/19 PROGRESS MAP).

Photos (March 13, 2019)
Photo 5
Photo 2 Photo 6
Photo 3 Looking up from Berm
Photo 4 Sand Quality

3/10/19 - Great Lakes Dredge & Dock has made some nice progress in less than 48 hours of starting the project (pictures below), and have completed ~1,000 linear feet of beach thus far (see 3/10/19 UPDATE).  The sand quality is excellent visually speaking.   We have received a lot of questions regarding how the dune feature will be constructed and tied into the existing, scarped dune that characterized Bogue Banks after hurricane Florence.  Hopefully this schematic next to an actual constructed portion will provide a good mental image = dune construction image

Photos (March 10, 2019)
Photo 7
Photo 2 Photo 8
Photo 3 Photo 9
Photo 4 Photo 10
Photo 5 Photo 11
 Photo 6 DUNE CONSTRUCTION EXAMPLE 

3/8/19 (PROJECT START) – Right on schedule.   The dredge Liberty Island arrived earlier this morning from Charleston, S.C., underwent a series of mandatory inspections, and subsequently excavated, sailed, and delivered the first hopper load of sand to Reach 3 at roughly 4:15 pm  (pictures below).  Note that beach nourishment will first be progressing eastward off the 1st subline landing (depicted here).  Also, the second subline has been installed today at Reach 2 (see “Station 514+00” here).      

Photos (March 8, 2019)
 Dozers Sculpting Dune ahead of Subline  Pumping Sand/Water
Pumping Zoom   Crab and Dredge Pipe
 Pumping looking east  Pumping looking east (2)

3/6/19 (tentative start date is Friday, 3/8/19) - The dredge Liberty Island is presently docked in Charleston, S.C. and will be transiting to Morehead City Harbor over the course of the next day(s) with dredging/pumping activities scheduled to initiate Friday afternoon/early evening (3/8/19) subsequent to mandatory vessel inspections - again in Reach 3, Indian Beach (see updates below).

Other dredging work in the area - It is also noteworthy to mention the hopper dredges Dodge Island and Padre Island started dredging maintenance work for the Morehead City Harbor Federal Navigation Project on February 26th and will likely conclude at the end of March.  Shoal material will be dredged predominantly from Range A and placed in the new nearshore berm east offshore disposal site (see image).  This scope of work is part of a regional hopper approach for the Brunswick, Savannah, Wilmington, and Morehead City Harbors  (~700,000 cubic yards for Morehead City - bid abstract).

Also a second federal contract for Morehead City Harbor maintenance, which represents a carryover project from the previous fiscal year was also awarded to Great Lakes Dredge & Dock utilizing a pipeline dredge (bid abstract).  The dredging ranges include both the Cutoff and Range A utilizing either the nearshore berm east or west disposal sites (see image), and will likely start sometime in April (~1,600,000 cubic yards).

And lastly the Corps of Engineers’ small hopper dredge, the Murden should be arriving to the area in the middle of March and will service both Morgan Creek (~6 days of dredging and ~7,500 cubic yards) in Range 1  (map)  and Bulkhead Channel (~4 days of dredging and ~ 3,596 cubic yards) in Range 1 (map).   Offshore disposal at the nearshore berm west.    

2/26/19 - The first submerged pipeline (“sub-line”) landing was transited to and installed earlier today at Reach 3 in Indian Beach at Station 695+50 (pictures below) as land based pipe continues to be delivered to the Indian Beach 4WD Ramp.       

Photos (Feb. 26, 2019)

2/25/19 - Land-based piping has begun arriving at the Indian Beach 4WD Ramp is actively being staged along the beachfront (pictures below). 

Photos (Feb. 25, 2019)

2/20/19 - Both the Indian Beach 4WD Ramp and Dog Leg 4WD Drive Access will be used to transfer land-based dredge pipe arriving via flatbed trucks to the beach.  Front-end loaders and other ancillary equipment should arrive at the Indian Beach 4WD Ramp early next week.  Some sub-line (water-based piping), derricks, barges, etc. have arrived and are holding tight in Bogue Sound, situated just north of Ft. Macon.   Otherwise, there are no schedule changes to report as the dredge Liberty Island is planned to initiate dredging/nourishment the first week of March in Indian Beach (Reach 3) and will be accompanied by the Ellis Island several weeks later - the temporary sub-line pipe landing locations from offshore as depicted for Indian Beach/Salter Path and East Emerald Isle remain the same.  

2/14/19 - No schedule changes to report.  The dredge Liberty Island is planned to initiate dredging/nourishment the first week of March in Indian Beach (Reach 3) and will be accompanied by the Ellis Island several weeks later - the temporary pipe landings from offshore as depicted for Indian Beach/Salter Path and East Emerald Isle remain the same.  Mobilization of dredge pipe, ancillary vessels, and equipment to the area should be more pronounced in the weeks ahead.

1/30/19 – There will be three temporary pipeline landings that will serve the dredges Liberty Island and Ellis Island.  In general the sand will be pumped ashore from the hopper dredge and progress east or west, then reversed as generally depicted in the new updated maps for Reach 2 and 3 (see - Indian Beach/Salter Path) and Reach 1 (see - East Emerald Isle).  The Liberty Island will arrive on site likely the first week of March followed by the Ellis Island.   

1/22/19 – Great Lakes Dredge & Dock should begin mobilizing land- and water-based pipe, heavy equipment, personnel, etc. towards the latter parts of February and although the schedule is tentative, dredging/pumping could begin the first week of March.

HOW TO INTERPRET THE PROGRESS MAPS
for The Post Florence Renourishment Project

 

The Post Florence Renourishment Project will utilize 945,446 cubic yards (cy) of sand obtained from the Offshore Dredged Material Disposal Site (ODMDS) associated with Morehead City Federal Navigation Project.  Emerald Isle (EI), Indian Beach (IB), and the unincorporated area of Salter Path (SP) will receive 617,131 cy,  271,905 cy, and 56,410 cy, respectively along 5.2 miles of shorelines in three discrete reaches depicted in the Project Construction Map above. As a mental picture, a conventional dump truck holds roughly 15 cubic yards of dry sand. The project is scheduled to be conducted between the March 1 to April 30, 2019 construction window established to limit impacts to biological resources, and the dredging contract has been awarded to Great Lakes Dredge & Dock. The ocean-certified, self-contained hopper dredges Liberty Island and Ellis Island will be employed for the project.  Great Lakes will utilize an area near the "Dog Leg" 4WD Ramp in EI and the IB 4WD Ramp Parking Area as their main equipment staging facility and points of beach access for heavy equipment.

 

Hopper dredges utilize dragheads affixed to trailing-arm suction pipes mounted on both sides of the vessel (port and starboard). The dragheads loosen the sand on the bottom off the seafloor and deliver the material to the vessel’s “belly” via the suction arms. Subsequent to completing a “cut” and filling the hopper, the dredge will travel and discharge (pump) sand via a buoyed pipeline located offshore that extends to the pre-construction dry beach. A secondary “T-valve” discharge pipe is used to transport material in one direction (east or west), then the other along the beach to complete approximately 1 - 2 mile sections as lengths of pipe are added and subsequently broken down. The buoyed pipeline and T-valve assembly is subsequently transited down the beach until the nourishment reaches have been filled. Dredged sand will be bulldozed into general construction specifications for subsequent grading into final contours, possibly tilled, and opened for recreational use.  The dredges Liberty Island has a maximum capacity of 6,540 cy and the Ellis Island 14,800 cy under optimal conditions.

 

Project engineers use “stations” positioned along the beach to monitor construction progress and to verify in-place volumes of sand pumped on the beach by dredging contractors. The progress maps above provide detailed views of the Post Florence Renourishment Project reaches to be completed in 2019 with the location/identification of the station numbers and the location of buoyed pipelines. The shaded areas in red represent the completed portions of the project and will be updated on a weekly basis throughout the construction.

The station numbers included in the progress map conveniently correspond to thousands of linear feet along the beach. For instance, the distance between station “418+00” (15th Street) and “473+00” (5th Street) on the Reach 1 - East Emerald Isle Area of Detail graphic above is 5,500 feet. If you visit the beaches of Bogue Banks this winter, you may see wood or metal stakes at the base of the dunes that will identify these station numbers as such.

PROJECT PLANNING & IMPLEMENTATION

 

The geographical extents and basic geometries of the Post Florence Renourishment Project are included in the accompanying maps below and the project is essentially a re-formulation of a nourishment project that was planned for this winter (2018-19) along the shorelines of EI, IB, and SP.  Hurricane Florence passed by Bogue Banks in September 2018 and just before the project was bid.  This same reach of beach lost ~945,000 cubic yards of sand in the wake of Florence and accordingly we re-focused our efforts, made a few slight changes, and re-termed our project to the Post-Florence Renourishment Project (Phase I).  This best describes what we are trying to accomplish, and is more consistent for FEMA reimbursement purposes.  Decisions from FEMA concerning reimbursement for beach nourishment or their “428” program, which provides a fixed-cost number in lump-sum will be made later this year (2019).  Great Lakes Dredge & Dock furnished the lone bid for the project bid totaling $20,109,385.  We have internally added some safety-net, contingency funding that increases the total to $20,910,385.  Maps and a Fact Sheet summarizing the cost schedule and geographic ranges of the project are below.  Phase II of the Post-Florence Renourishment Project is tentatively scheduled for winter 2019-2020 and will encompass Central and Western EI, Pine Knoll Shores, and East Atlantic Beach. 

In cross-section going from the top of the dune seaward, the beachfill will be contoured by; (1) tying into the existing, eroded frontal dune at +12 feet NAVD 88 and maintaining that top dune elevation at vary lengths as one progresses seaward, (2) the slope of the newly constructed frontal dune will be graded on a 5:1 slope to the elevation of +6 feet NAVD 88, (3) the beach berm (flat part of the beach) will be extended from that point seaward at +6 feet NAVD 88 at varying lengths, and (4) the slope of the fill from the berm crest out to sea will be on a 20:1 slope.  The newly created dune crest and dune slope will be planted (vegetated) with Sea Oats and Bitter Panicum as part of the contract (see typical cross-section below).     

Fact Sheet: Florence (2019)

 

 

The borrow source for this nourishment effort is the Offshore Dredged Material Disposal Site (ODMDS) associated with Morehead City Federal Navigation Project. This dump site is essentially a repository for dredged material historically extracted from the Outer Harbor reach of the navigation channel and based upon experiences with a 2004 and 2007 Section 933 Project that utilized channel material for beach nourishment and 2004, 2007, and 2013  post hurricane projects that actually utilized the ODMDS; we expect the sand quality to be excellent. This also makes intuitive sense, because for the most part, the shoal material that enters the navigation channel at Beaufort Inlet is sand that has traveled from adjacent beaches. Construction, or deepening material that resides in the ODMDS should be avoided. To this effect the firm of Moffatt & Nichol, who has been retained by the Bogue Banks communities as the engineering consultant for the Post-Florence Renourishment Project, has performed additional sediment sampling and analyses in the ODMDS to hone the areas of beach quality sand.